Update News about South Korea Customer’s Cow Farm Floor Grid Construction
As our preview reported that our South Korea Customers visited our factory and place an order on May 4th (click here).
The total paving installation area is 2250sqm. After the customers came back to South Korea, they made the gravel stabilization grid installation plan quickly.
June 7th – June 9th. Three days for basic level construction. The total basic level is 30cm as we discussed before. Use 20cm pebbles and 10cm stone powder to reinforce the basic level.
June 10th unload the gravel stabilization grid.
June 11th – June 9th Two days for grid paving. The installation time is quite short, which is thanks to Leiyuan plastic gravel grid unique design for time saving and strong structure.
June 13th the floor construction of the cow farm is totally finished and the farm is officially put into use. The cow are very fond of newly paved sports venues.